Dundalk Construction - 2 Week Forecast

Main St, Ida St, and Osprey St Reconstruction in Dundalk

Ida Street and Main Street (Ida Street to McAuley Street)

  • Base course asphalt to be placed next week (August 17-21)
  • Followed by sidewalk construction and landscaping operations
  • Intersection of Main Street and Ida Street will remain CLOSED for the Contractor to safely complete their work

 Main Street (McAuley Street to Proton Street)

  • Excavation operations for watermain and storm sewer servicing will continue
  • Road is closed with access only provided to local residents/businesses. 
  • Individual driveway access may be temporarily impacted as excavation operations progress.

Osprey Street

  • New watermain commissioning (testing) ongoing on Osprey Street South.
  • Excavation operations for watermain, storm sewers and watermain servicing will continue in the Owen Sound Street intersection for approximately one more week.
  • Hydro One to relocate select hydro poles on Osprey St North once Contractor has completed underground excavation operations.
  • Road is closed with access only provided to local residents/businesses. 
  • Driveway access may be temporarily impacted as excavation operations progress.
  • Intersection of Main Street and Osprey Street, will remain CLOSED for Contractor to safely complete their work.

Thank you for your patience and cooperation as this work continues. For more information, please visit our website: https://www.southgate.ca/