Dundalk Reconstruction Weekly Update

Main Street, Ida Street, and Osprey Street Reconstruction in Dundalk Update

Ida Street and Main Street (Ida Street to McAuley Street)

  • Base course asphalt was placed week of August 17th
  • Sidewalk preparation and construction planned for next week (August 24-28)
  • Intersection of Main Street and Ida Street will remain CLOSED for the Contractor to safely complete their work

 Main Street (McAuley Street to Proton Street)

  • Excavation operations for watermain and storm sewer servicing will continue
  • Road is CLOSED with access only provided to local residents/businesses.
  • Individual driveway access may be temporarily impacted as excavation operations progress

Osprey Street

  • New watermain commissioning (testing) complete on Osprey Street South
  • Preparation for curb construction on Osprey Street South planned for next week (August 24-28)
  • Excavation operations for watermain, storm sewers and sanitary servicing is complete
  • Hydro One is scheduled to relocate select hydro poles on Osprey Street North in the coming weeks
  • Osprey Street is CLOSED with access only provided to local residents/businesses
  • Intersection of Main Street and Osprey Street, will remain CLOSED for Contractor to safely complete their work

Thank you for your patience and cooperation as this work continues. For more information, please visit our website: https://www.southgate.ca/